Burhaniye (Balıkesir) Waste Water Network Project

BURHANIYE (BALIKESIR) WASTE WATER NETWORK PROJECT

 

PROJECT TYPE

 

EPCM, Fixed Price

SERVICES PROVIDED

 

  • Design and Planning
  • Construction Supervision and Quality Control
  • Construction and Project Management
  • Feasibility Studies
  • Technical Specification
  • Geotechnical Engineering
  • Environmental Assessment and Hydrological Studies
  • Urban Development
  • Administrative Support and Approvals
  • Cost Management
  • Risk Management
  • System Certifications

BACKGROUND

 

The tendering authority for all of our infrastructure projects is T.C.İller Bankası. T.C. İller Bankası is the governmental institu¬tion who provides the funding, tendering and supervision of most of the municipal infrastructure projects. These projects were constructed by PROCCEA under contract with T.C.İller Bankası.

 

PROJECT DESCRIPTION

 

The waste water projects consist of main collector line, elevation lines, elevation centers, pumping stations, network and treat¬ment plant components. A mix of steam-cured concrete and fibreous glass reinforced plastic pipes were used.

  • 40km. waste water network (200-500mm radius),
  • Elevation Centers,
  • 2 Pumping Stations,
  • 5km. Elevation Line (400mm radius),
  • Waste water treatment plant (60lt/sec),

 

STATUS

CONTRACTED AS

CLIENT

COMPLETION

Completed

EPCM, Prime Contractor

T.C. İller Bankası

1997

DESIGN PERIOD

CONSTRUCTION PERIOD 

   

70 days

24 months