Ouagadogou Gold Mine

OUAGADOGOU GOLD MINE , BURKINA FASO

AVOCET MINING PLC (WEGA MINING) ADR PLANT

 

PROJECT TYPE

 

Prime Contractor

SERVICES PROVIDED

 

•  ADR Plant & Structural Steel Manufacturing

•  Commissioning & Start-Up

•  Staff Training

BACKGROUND

 

Inata Ouagadogou gold mine  operations in Burkina Faso are located within a highly prospective 1,660 km2 land package in the Bélahouro district approximately 220 kilometres north-east of the capital, Ouagadougou. The Bélahouro district is on the eastern edge of the Birimian greenstone belt. The Inata gold deposit is deeply weathered with the base of complete oxidation extending down to depths of 60m. A transitional zone of moderate oxidation extends down to more than 150m depth. The Inata deposit presently comprises mineral resources of 4.69 million ounces and an ore reserve of 0.92 million ounces. The average grade of the mineral Reserves is 2.07 grams per tonne. This project is the first gold mine project in Burkina Faso with a very long project life. With the help of this project local people will find a chance to get trained on the operation of plant.

BENEFITS TO CUSTOMER

 

  • All local staff have been trained by CH Engineering highly experienced site team
  • In shortest time, frame all equipment have been started up and ready for operation
  • Maintenance tips will improve life times of all equipments started up by ch engineering site team

PROJECT DESCRIPTION

Inata Ouagadogou gold mine  has CIC process and 4 tons of ADR Plant. As we CH Consultants, we completed 120 tons of structre steel manufacturing, erection, Over 2500 meter of carbon steel and HDPE piping and ADR equipment installation and start - up

 

STATUS

CONTRACTED AS

CLIENT

COMPLETION

Completed

Supplier & Supervisor

Avocet Mining PLC.

2009

DESIGN PERIOD

CONSTRUCTION PERIOD

 

150 days

365 days