Maaden Al- Amar Gold Mine

MAADEN AL - AMAR GOLD MINE, SAUDI ARABIA

ADR PLANT

 

PROJECT TYPE

 

Prime Contractor

SERVICES PROVIDED

 

  • Gold Room Installation
  • Stripping Cells Installation
  • Acid Place Installation
  • Start-up & Commissioning
  • Staff Training

BACKGROUND

 

Al Amar is located approximately 195 km southwest of Riyadh. It comprises an underground mine which is planned to process a gold rich polymetalic ore at a rate of 200 ktpa to produce gold in dore and copper and zinc concentrates which are sold to third parties for toll smelting. Processing will involve crushing, grinding, copper flotation, and recovery of gold from the copper flotation tailings by CIL technology and zinc flotation. Its products will be copper concentrate, dore and zinc concentrate, which will all be sent abroad for refining. This project is closely observed by other investors because of its importance to Saudi Arabia. Due to that reason CH Engineering served client with the best & fast installation, start up and training. Plant started before planned schedule and without problem or incident.

BENEFITS TO CUSTOMER

 

  • Training of Staff by CH Engineering Highly Experienced Supervisors
  • Risk Free Start-up and Operation

 

 

PROJECT DESCRIPTION

 

Al Amar gold mine has CIC carbon system and 4 tons ADR plants. CH Supervisor team and site team had completed 110 ton of Structural Steel Erection, all of ADR equipment installation and start – up, over 2000 meters of CS and HDPE piping plant and training of the staff. 

 

STATUS

CONTRACTED AS

CLIENT

COMPLETION

Completed

Prime Contractor

Maaden

2008

 DESIGN PERIOD

CONSTRUCTION PERIOD

 

 90 days

60 days