Çöpler Gold Mine
ÇÖPLER GOLD MINE, ERZINCAN, TURKEY
ÇUKURDERE MINING LTD. ADR PLANT
PROJECT TYPE
Prime Contractor
SERVICES PROVIDED
- Design and Manufacturing the CIL Columns of ADR Plant
BACKGROUND
Çöpler is located in the eastern part of Turkey, roughly 550 km east of Ankara and 120 km southwest of the city of Erzincan. The nearest population center is the town of ĺliҫ (population 2,500) which is 6km northeast of Çöpler. Çöpler’s attributable Proven and Probable Reserves totalled 74.4 Mt at an average grade of 1.4g/t gold for a total of 3.5 million contained ounces. The project is one of the important new gold mining investment in Turkey. High quality manufactured steel tank with special rubber inner lining for the chemical and detox preparation system
BENEFITS TO CUSTOMER
- High Quality Manufactured Steel Tanks
• High Strength Rubber Lined Steel Tanks
PROJECT DESCRIPTION
Çöpler Gold Mine has 4 tons of CIC and ADR plant, in this project scope, we completed design manufacture and transportation of CIC of ADR plant for increase CIC system capacity.
STATUS US Completed |
CONTRACTED AS Prime Contractor |
CLIENT Çukurdere Madencilik |
COMPLETION 2008 |
DESING PERIOD | CONSTRUCTION PERIOD | ||
90 days | 150 days |