Tropicana Hotel, Paramaribo, Suriname
TROPICANA HOTEL, PARAMARIBO, SURINAME
4 STAR 90 BEDROOM HOTEL
PROJECT TYPE
Fixed Price and Cost Plus, EPCM
Proccea’s owners were the prime contractor with their 100% owned local company
SERVICES PROVIDED
- Engineering and Design
- Three Stage Procurement on Cost Plus Parts
- Logistics
- All Construction Services
- Management of Design and Construction
- Risk Management
BACKGROUND
The hotel was built as an extension of an existing casino which was also completed by proccea. Hotel brought Suriname a chance to attract higher class tourists not only from long distances but also from neighbors. The contract was started as fixed price however due to project changes a significant modification had been completed as cost plus without any extension to the programmed opening. Existing facilities continued their activities and no major problems were experienced. Our prior hotel experience in the same region made this project progress smoothly on material delivery. While this is the only premium hotel in the area the 90 room hotel is ranked as 4 star.
BENEFITS TO CUSTOMER
- Best Hotel on the Area
- Single Point of Contact
- Fixed Price Product Delivery in This Very Unstable Region
- On Programme Delivery
- Continued Use of Existing Facilities
PROJECT DESCRIPTION
Reinforced concrete construction of 90 rooms. Central cooling with variable refrigeration flow allowed a huge saving.
Hotel has 90 rooms, 2 restaurants, one casino, open swimming pools, a spa, tennis court, parking space for 250 cars and landscaped areas of 25.000 m2 mechanical and electrical systems were designed to the latest technologies.
STATUS Completed |
CONTRACTED AS EPCM, Prime Contractor
|
CLIENT PGG International
|
COMPLETION 2005
|
DESIGN PERIOD |
CONSTRUCTION PERIOD |
SIZE OF FACILITY | |
85 days
|
155 days |
8700 m2
|