ANCOP SSB Gardez, Paktika, Afghanistan

ANCOP SSB GARDEZ, PAKTIKA, AFGHANISTAN

DESIGN AND CONSTRUCTION OF AFGHAN NATIONAL CIVIL ORDER POLICE STATIONS FOR 541 PAX ( USACE ) .

 

PROJECT TYPE

 

Fixed Price

SERVICES PROVIDED

 

  • DOD Based Design and Engineering
  • De-mining
  • Local Security Control
  • Quality Control System
  • Logistics
  • All Construction Services
  • Management of Construction and Design

BACKGROUND

 

The proposed site is located 7km South of Gardez City, the Provincial Capital of Paktya and approximately 135 km Southeast of Kabul Province. The site’s average elevation is 2,303 meters. The site is owned by the Ministry of Interior. The Contractor shall provide site adapt design and construction of standard building designs, the Utility Infrastructure, and Civil Infrastructure.

 

 

BENEFITS TO CUSTOMER

 

  • Expertise on Unsecure Areas
  • Hard Terrain Adaptation
  • Zero Safety Records
  • Online Project Tracking
  • Full Integration of Customer
  • Land Dispute Solution

 

 

 

 

PROJECT DESCRIPTION

 

This project consists of the design and construction of site improvements and construction of facilities to support the Afghanistan National Police (ANP) Units: ANCOP Headquarters and Special Support

Battalion located in Gardez, Paktya Province, Afghanistan. This project is defined as the management, design, material, labor, and equipment to design and construct and/or refurbish all utilities, roads, buildings, force protection measures, site security, de-mining activities.Security is critical to construction in Afghanistan, especially on roads and remote areas away from Coalition Force bases.

Steel Structure DOD certified buildings of training building, DFAC and ECP and other buildings are latrine, barracks, warehouse, Administration Building, Ammunition Supply, guard towers, gate house and a well house and organic waste disposal plant. Also the complex is powered by a generator.

STATUS 

Active

CONTRACTED AS

Prime Contractor

 

CLIENT

US Army Corps of Engineers

 

 

COMPLETION

On-going

 

 

DESING PERIOD

 CONSTRUCTION PERIOD

SIZE OF FACILITY

 

 90 days

650 days

180000 m2