Afghanistan National Police, Islam Qala

 

AFGHANISTAN NATIONAL POLICE,  ISLAM QALA

2ND BATTALION BORDER POLICE HEADQUARTERS 

 

PROJECT TYPE

 

Fixed Price

SERVICES PROVIDED

 

  • Engineering and Design
  • Quality Control System
  • Three Stage Procurement Logistics
  • All Construction Services
  • Management of Design and Construction
  • Local Land Dispute Solutions

BACKGROUND

 

The Border Police Battalion Headquarters in Islam Qala, Herat, Afghanistan project consist of the design and construction of the facilities. The project site is located near by the Islam Qala Border and Afghan National Police had already occupied the site due to the old administration building being refurbished as a part of the contract. These soldiers had been moved to temporary facilities before the construction started.

 

BENEFITS TO CUSTOMER

 

  • Experience and Familiarity with the Region
  • High Quality
  • Ability to Perform Risk Analysis
  • Turnkey Delivery of a Complex Project in a War Zone
  • Flexibility on Aproach
  • Early Project Completion

PROJECT DESCRIPTION

 

This project consists of the design and construction of the facilities for the Border Police Battalion Headquarters at Islam Qala. This project is defined as the design, material, labor, and equipment to construct and/or refurbish all utilities, roads, buildings, force protection measures, site security, de-mining activities and other features. This project consist of a police compound typically containing a water well, sanitary sewer system, power generation building, barracks, latrines, administration and storage buildings, pavements, guard towers and security walls.

 

STATUS 

Completed

CONTRACTED AS

Prime Contractor

 

 

CLIENT

US Army Corps of Engineers

 

 

COMPLETION

2007

 

DESIGN PERIOD

CONSTRUCTION PERIOD

SIZE OF FACILITY

 

 60 days

240 days

4000 m2