Adıyaman Potable Water Supply Project
ADIYAMAN POTABLE WATER SUPPLY PROJECT
PROJECT TYPE
EPCM, Fixed Price
SERVICES PROVIDED
- Design and Planning
- Construction Supervision and Quality Control
- Construction and Project Management
- Feasibility Studies
- Technical Specification
- Geotechnical Engineering
- Environmental Assessment and Hydrological Studies
- Urban Development
- Administrative Support and Approvals
- Cost Management
- Risk Management
- System Certifications
BACKGROUND
The tendering authority for all of our infrastructure projects is T.C.İller Bankası. T.C. İller Bankası is the governmental institu¬tion who provides the funding, tendering and supervision of most of the municipal infrastructure projects. These projects were constructed by PROCCEA under contract with T.C.İller Bankası.
PROJECT DESCRIPTION
The potable water supply projects consist of water transport, storage, pumping stations and network components. A mix of pvc, steel and asbestos-cement pipes were used.
- 380km. water supply network (150-500mm radius]
- 25km. water transport line (600mm radius)
- 5000 m3 and 3000 m3 underground water resorvoirs
- Pumping stations
STATUS |
CONTRACTED AS |
CLIENT |
COMPLETION |
Completed |
EPCM, Prime Contractor |
T.C. İller Bankası |
1998 |
DESIGN PERIOD |
CONSTRUCTION PERIOD |
||
120 days |
36 months |