Adıyaman Potable Water Supply Project

ADIYAMAN POTABLE WATER SUPPLY PROJECT

 

PROJECT TYPE

 

EPCM, Fixed Price

SERVICES PROVIDED

 

  • Design and Planning
  • Construction Supervision and Quality Control
  • Construction and Project Management
  • Feasibility Studies
  • Technical Specification
  • Geotechnical Engineering
  • Environmental Assessment and Hydrological Studies
  • Urban Development
  • Administrative Support and Approvals
  • Cost Management
  • Risk Management
  • System Certifications

BACKGROUND

 

The tendering authority for all of our infrastructure projects is T.C.İller Bankası. T.C. İller Bankası is the governmental institu¬tion who provides the funding, tendering and supervision of most of the municipal infrastructure projects. These projects were constructed by PROCCEA under contract with T.C.İller Bankası.

 

PROJECT DESCRIPTION

 

The potable water supply projects consist of water transport, storage, pumping stations and network components. A mix of pvc, steel and asbestos-cement pipes were used.

  • 380km. water supply network (150-500mm radius]
  • 25km. water transport line (600mm radius)
  • 5000 m3 and 3000 m3 underground water resorvoirs
  • Pumping stations

STATUS

CONTRACTED AS

CLIENT

COMPLETION

Completed

EPCM, Prime Contractor

T.C. İller Bankası

1998

DESIGN PERIOD

CONSTRUCTION PERIOD

   

120 days

36 months